Grid Collapse: TCN Aims for Repairs in Three Weeks

Efforts to resolve Nigeria’s frequent national grid collapses and stabilize electricity supply are expected to take a minimum of three weeks, according to the Transmission Company of Nigeria (TCN). The country experienced two grid collapses this week, making a total of 11 so far this year.

TCN has identified three key hubs—Shiroro in Niger State, Jebba, and Ganmo in Kwara State—as primary sources of the recent collapses due to abnormal high-frequency activities. Heavy equipment is being transported to these hubs to aid in repairs, with the aim of restoring stability to the power grid.

According to TCN’s Executive Director of Transmission Services, Gbenga Ajiboye, the ongoing maintenance work involves relocating equipment from other substations across the country. By noon on Friday, some regions had power restored, with the generating companies producing 1,844MW by 4 PM.

TCN’s Public Affairs General Manager, Ndidi Mbah, attributed the most recent collapse to a sudden frequency spike, which forced the shutdown of one of TCN’s substations to prevent further damage. Repair work is focused on critical transmission lines, including the Shiroro–Mando axis and Jebba Transmission Substation upgrades.

The Minister of Power, Adebayo Adelabu, acknowledged the grid’s vulnerabilities, citing aging infrastructure, vandalism, and past maintenance neglect as major issues. Adelabu indicated plans to seek supplementary budget approval to implement the committee’s recommendations, which aim to prevent future collapses. The committee’s report includes suggestions for testing equipment at critical nodes, improving capacity development for maintenance staff, and modernizing the grid infrastructure with enhanced Supervisory Control and Data Acquisition (SCADA) systems.

In response to ongoing grid instability, the Lagos State Government has invited bids from investors for the construction of 4GW gas-fired power plants. The initiative is part of the state’s Clean Lagos Electricity Market plan to address its power supply deficit, which currently sees Lagos receiving only 2GW of its 6GW demand from the national grid.

About AkoniTV

Check Also

CBN Retains Interest Rate at 26.5%

The Central Bank of Nigeria on Wednesday retained Nigeria’s interest rate at 26.5 per cent ...

Leave a Reply

Your email address will not be published. Required fields are marked *